Need explanation for your answer. Noguessing. 8 dollar credit for correct answer Each of the following is TRUE of an Activity Network DiagramEXCEPT A….

Need explanation for your answer. Noguessing. 8 dollar credit for correct answer

Each of the following is TRUE of an Activity Network DiagramEXCEPT

A.) Each activity is plotted in the order of what needs tobe done first, second, etc

B.) The time expected to accomplish each activity is notedon the diagram

C.) The importance of each task is used to define thecritical path

D.) The diagram illustrates tasks that may be performed inparallel or at the same time ( concurrently)

Order the answer to view it

Assignment Solutions
Assignment Solutions